What is the sequence for opening and closing a quick-opening valve when blowing down a boiler?

Prepare for the Black Seal TC Exam. Access flashcards and multiple-choice questions, each with explanations and hints. Elevate your readiness!

The correct sequence for opening and closing a quick-opening valve when blowing down a boiler is to first open the valve and then close it afterward. This procedure ensures that the boiler is safely and effectively purged of any accumulated sludge, steam, or water.

Opening the valve first allows for the immediate release of pressure and contents within the boiler, which is critical for maintaining operational safety. By following this sequence, it minimizes the risk of pressure build-up that could result in a hazardous situation.

Once the blowdown is complete and the needed maintenance or checks have been performed, closing the valve at the end prevents any unnecessary loss of water or steam, allowing the boiler to return to normal operating conditions securely.

This methodical approach underscores the importance of safety and efficiency in boiler operation, ensuring that each step is carried out in a logical and precise manner.